BRIDGE AND BOARD OF DIRECTORS INFORMATION UPDATES 8/1/14

 

 

 

 

The bridge has completed it’s journey across the river and now rests on the abutments on each side.  The coming week will see the east side approach built, decking installed and final concrete pour completed on the west side.  It’s getting close but still lots to do!!  Now looking at late the week of Aug. 11th for opening.  Watch this site for final opening date.

 

 

Agreement letters and gate codes for those who are paid in full or making payments on their assessments will be mailed out next week.

By vote of the MIR Board of Directors Zan Oliphant has been removed from the board for conduct detrimental to the board and community.