Canyon Falls Bridge Progress Report

 

 
The elaborate roller system being constructed to "launch" the bridge is taking longer than scheduled.  Abutment construction was completed ahead of schedule and under budget but now the schedule is about 4 days behind, not unusual in a project of this type.  The contractor hopes to make time up in the bridge assembly and launching phase.  Best estimate of completion date is now toward the end of the first week of August.
 
We now have 70% of owners paid or making payments on their assessments and we hope as bridge completion date approaches more owners will start paying, allowing them access to the bridge.  79 owners have not made any payment toward their assessments.  THANK YOU! to the 170 owners who are paying for the Canyon Falls Bridge!