Canyon Falls Bridge update

 
 

  1. All permits for bridge construction are in hand.
  2. PUD is finalizing details with BNSF for a license to use BNSF roads. 
  3. The bridge is on order it will be released for shipping to arrive when the bridge construction company will be on site.
  4. Coordination with the bridge construction company start date is presently being negotiated.
  5. Details for access to SR-2 are being finalized.
  6. Community loans are being finalized. We will be depositing $120,000 of community loans into the MIRCC bank account on Tuesday the 27th.
  7. Special assessments are at $52,500 collected, with more coming in every day.
  8. Above the slide amount currently in the bank is $60,000.
  9. Below the slide currently in the bank is $21,000.
  10. On Tuesday the 27th we will have the funds in hand necessary to Construct the bridge.
  11. Construction of the bridge should start in June, we will keep everyone updated on a start date, as details are finalized.  

Thank you very much, Earl!

Thank you very much, Earl!

An informed community is a happier community. =0)